|
|
Best if printed in landscape.
Priority
Who
has the superior water right? What date is the basis for establishing
priority? How soon must the water be put to a beneficial use?
City
and County of Denver v. Northern Colorado Water Conservancy District,
Colorado, 1954
(p. 55 of Gould's 7th ed.)
- The
city of Denver was intending to divert water from the western side of
the continental divide for use by the city on the eastern side.
- 1914
-- examined the western slope
- 1921
-- employed a firm to survey the area of Fraser and Williams Fork
- 1922
-- preliminary survey and filed map and statement with state engineer
-- Blue River
- 1926
-- another survey showing (second) lower tunnel -- Blue River
- 1927
-- another filing showing a third site for the tunnel
- 1941
-- additional engineering work showed a dam and reservoir, and relocated
tunnel
- 1946
-- work began on this last tunnel
- Denver
claimed priority based on 1921 and 1927
- Conservancy
District claimed priority date of 1937 and opposed Denver's claims
- District
court granted Denver a water right based on smaller tunnel with a priority
date of 1946
- Denver
appealed.
- Supreme
court upheld district court.
- An
appropriation is not complete until actual diversion and use is completed,
but the right relates back to time the first open step was taken giving
notice of intent to secure the water right.
- The
right to relate back is conditional in that construction of the project
be pursued with "reasonable diligence," and the applicant
have a fixed and definite purpose to take the project and carry it through.
- Surveys,
preparation of maps, acquiring rights of way and option, obtaining a
contract to carry water through the tunnel, drilling test holes, clearing
timber, are sufficient to satisfy requirement of reasonable diligence.
- But
Denver spread its activities over 20 years, whereas in the case being
relied on for precedence, the applicant made the efforts in a 5-year
time span.
- Diligence -- steady application, constant effort, doing an act or series of acts
with all possible expedition, with no delay except such as may be incident
to the work itself.
- Court
argued that Denver did not even arrange financing for the project during
the 20 years; therefore priority was granted on the basis of the later
date.
-
Dissent: Some changes in the plan can be tolerated without the
loss of priority. When is construction on one part of a large
project enough to protect the entire project? The dissent would answer
this question as: when the part relates to a single integrated purpose
so that progress on one part has a direct bearing on another part.
Interruption in the effort due to depression and war -- uncontrollable
events -- justify the slow progress in construction and financing.
Processes for Determining Water Rights
A basic premise of prior appropriation doctrine is that the user who first puts water to a beneficial use has the highest or best legal right to continue to use the water. During times when there is not enough water for all users, the last person to put the water to a beneficial use will be the first one required to discontinue their use. Restated, priority determines relative legal rights among users appropriating water from the same source, and priority is based on the date the user first put the water to a beneficial use. A challenge is how to determine and document when a user put water to a beneficial use.
- The legal system relied on the courts to resolve disputes involving priority dates but this system became cumbersome (and perhaps inconsistent) as each appropriator litigated with each other appropriator.
- The next step to simplify the process was for the courts to adjudicate the water rights (quantity, priority, etc) for all appropriators drawing from the same source (such as a river) in a single judicial action. This is referred to as a general adjudication.
- In North Dakota and several other states, priority dates from the time the user files an application for a (conditional)
permit, or putting the water to use if a permit is not needed. See
N.D.C.C. §§61-04-06.3
and 61-04-02. Also see N.D.A.C. §89-03-01-12.
- Restated,
priority dates from when the project was started; not when the water
was put to a beneficial use. This legal principle of "relation back" recognizes the investment
that often is needed to construct a water project.
Prior
to permit systems, the earliest that priority could arise would be when
the first step of the project was taken. See
author's note for the idea that priority may date back to a time before
applying for a permit (notice of intent to file an application in New
Mexico).
How much time does an appropriator (the holder of a conditional permit)
have to put the water to a beneficial use?
- The
amount of time can be "as long as it takes provided the appropriator
is using reasonable diligence to complete the project throughout this
period;" e.g., Colorado.
- Principle
of "reasonable diligence" is to prevent someone from acquiring
a right in the water without intent of putting it to a beneficial use.
Recall that intent to use the water is one of the basic requirements
of acquiring a water right.
Are there circumstances in which an interruption in reasonable diligence will be tolerated? Financial? Legal? Physical? Health?
- In North Dakota, there can be extensions of time for "good cause." N.D.C.C.
§61-04-14.
- N.D.A.C. §89-03-01-12. "Where the time has expired to put all or any portion
of the water of a conditional water permit to the beneficial use named
in the permit, the state engineer will notify the permittee of this
fact. The state engineer will provide the permittee with a form upon
which the permittee may request an extension for applying the water
to the beneficial use and to explain why an extension should be granted."
- The
requirement of reasonable/due diligence has been codified in some states.
-
Can a conditional permit be cancelled (for lack of reasonable diligence)
without the due process of notice and right to be heard?
How
quickly must the state take action on a permit application?
Priority dates from the time of filing the application; can a state agency
protect an undeveloped water right by "sitting on an application"
and thus not triggering the requirement that the applicant must initiate
development with reasonable diligence? Or is the agency required to respond
to an applicant within a specified period?
- Montana
-- M.C.A.
§85-2-310. Action on application. (1) The department shall
grant, deny, or condition an application for a permit in whole or in
part within 120 days after the last date of publication of the notice
of application if no objections have been received and within 180 days
if a hearing is held or objections have been received.
Must
subordinate users always discontinue their water use during shortages?
Basic
rule -- in times of water shortages, subordinate water users must discontinue
their water usage so the water is available to be used by those with priority.
But, must a subordinate water user relinquish their use of water if that
action will not improve the priority users' ability to receive water?
State
ex. Rel. Cary v. Cochran, Nebraska, 1940
(p. 64 of Gould's 7th ed.)
- Central
Power and others brought an action against the state to require the
state to properly administer the irrigation laws of Nebraska. Central
Power had priority to water in the Platte River as of 1882. Central
Power contends that the state, by allowing junior appropriators to use
water, is damaging Central Power's right to the water.
- The
Platte River loses water as it flows downstream due to evaporation and
percolation.
- The
state administrators allowed the upstream junior appropriators to use
the water rather than have it "lost" to nature.
- Central
Power argues that all subordinated water right holders upstream from
the Kearney Canal must cease their use if there is not enough water
to fill the priority rights at Kearney canal.
- However,
due to the heavy loss of water, the trial court concludes it would be
an unjustified waste to attempt delivery to the Kearney Canal (essentially
under the reasonable use theory that we talked about previously).
- On
appeal: water rights are subject to regulation by the state by virtue
of its police power. But the state administrator cannot change priorities.
Instead, the administrator must decide whether use of the water by junior
appropriators would damage the senior appropriators. If the answer is
no (that is, the senior appropriators would not receive any more water
even if the junior appropriators' use was restricted), the state administrator
can allow the junior appropriators to use water.
- This
court would not allow state administrators to weigh or consider the loss of the
water as it flows downstream to the priority user. That would give the administrators too much discretion.
- Restated,
as long as discontinuing an upstream subordinate use allows more water
to reach the downstream priority user, the subordinate use must be discontinued
even though this leads to a substantial loss of water as it flows from
the upstream users to the downstream users.
- Does this rule lead to inefficent
use of water?
- It
is referred to as "call" when a user with
priority demands that subordinated uses be discontinued, such as would
be necessary during time of a water shortage.
- During
time of a water shortage, why not proportionally reduce each users'
amount? Is there a physical reason, or just a political/legal reason?
- Consider the note on pp. 69-70 (Gould's 7th ed.) wherein the commentator suggests that priority is not strictly enforced.
- This
Nebraska case implies that a subordinate use will not be discontinued if that
action will not benefit the priority user (futile call).
- Can
a senior appropriator "call" on subordinate users of tributary
streams? Or are tributaries administered as being a water source separate
from the main stream or river? See N.D.A.C.
§89-03-01-08.
- Is
a use limited to a particular time of the year, or may the appropriator
draw the water whenever it can be put to a beneficial use?
- N.D.C.C.
§61-04-06.2. "The state engineer may issue a permit
subject to fees for water use, terms, conditions, restrictions,
limitations, and termination dates the state engineer considers
necessary to protect the rights of others, and the public interest."
Will
a subordinate domestic use have priority over a prior use for irrigation?
Will a particular type of water use prevail over a pre-existing alternative
use?
Phillips
v. Gardner, Oregon, 1970
(p. 72 of Gould's 7th ed.)
- Watermaster
threatened to cut off plaintiff's domestic water supply and drain their
impoundment in order to provide water to a downstream priority water
user.
- Court
enjoined watermaster from cutting off the domestic supply based on 1893
statute.
- Court
of Appeals disagreed and interpreted the 1909 statute as repealing conflicting
law and that "time of appropriation" will determine priority.
"Type of use" did not take precedence over "time of use"
in determining priority.
Again, consider the comments included on pp. 69-70 of Gould's 7th ed. Also note the South Dakota and Utah statutes described on p. 75 (e.g., domestic use is highest use).
Can
a new use be developed as long as the water it consumes is replaced?
Cache
La Poudre Water Users Ass'n v. Glacier View Meadows, Colorado, 1976
(p. 75 of Gould's 7th ed.)
- Developer
of residential lots filed two applications for approval of a plan of
augmentation.
- Water
users association objected.
- Developer
owns shares of irrigation company entitling it to stored and direct
flow water.
- Developer
will use water from wells for domestic purposes and use stored water
to replace the well water that is consumed. Developer will allot 26.7%
of the water to in-stream flow to replace the 25% of the water that
historically was return flow.
- Water
association argues there must be 100% replacement of the well water
or the senior appropriators will be harmed.
- Plan
of augmentation is a plan to increase supply of water, and will be approved
if it does not injure vested rights.
- Where
senior users can show no injury, they cannot preclude a beneficial use
by another. Water is available if the new use will not cause injury
to existing users.
-
Subordinate users can substitute water to meet the needs of downstream
priority users.
Priority
users cannot expand or change use if that will adversely impact subordinate
users (e.g.,
N.D.A.C. §89-03-02-11), but...
Priority
users are not protected from every injury or change that may occur from
a new use. N.D.C.C.
§61-04-06.3 "Priority ... does not include the right to
prevent changes ... if ..."
How
to move water from one use to another -- transfer? dedication? rotation
among users?
Last updated
January 31, 2007
|